目的:量化分析分布式光伏接入对110 kV变压器中性点过电压特性的影响,并评估现有保护间隙与金属氧化物避雷器(metal oxide arrester, MOA)协同保护策略的适应性。方法:基于电磁暂态程序(alternative transients program-electromagnetic transients program, ATP-EMTP)仿真平台建立含分布式光伏的110 kV输电系统模型,对典型故障工况下变压器中性点的过电压响应进行仿真与分析。结果:分布式光伏接入后,变压器中性点过电压的分布特性发生明显变化。在单相接地故障中,光伏的持续馈电会将中性点电压由41.8 kV抬升至43.6~72 kV的保护间隙放电临界区,显著增加间隙误动的风险;在两相断线故障中,光伏的接入虽可降低中性点过电压幅值,但会使电压由72.02 kV下降并进入临界区,导致保护间隙动作的可靠性下降,增加绝缘配合失效的风险。结论:传统保护判据已难以适应光伏接入后中性点过电压的新特征。本文提出的基于幅值-时间双重判据的可控间隙保护策略,可有效避免临界区内的误动与拒动问题。
Abstract:Aims: This paper aims to quantify the impact of distributed photovoltaic(PV)integration on the neutral-point overvoltage of 110 kV ungrounded transformers and to assess the adaptability of the coordinated protection scheme composed of a protective gap and a metal oxide arrester(MOA). Methods: A 110 kV transmission system model with distributed PV was established in the alternative transients program-electromagnetic transients program(ATP-EMTP); and the neutral-point overvoltage responses under typical fault conditions were simulated and analyzed. Results: Distributed PV integration significantly changed the distribution characteristics of neutral-point overvoltage. Under single-phase-to-ground faults, sustained current feeding from PV raised the neutral-point voltage from 41.8 kV to the critical gap discharge range of 43.6~72 kV, markedly increasing the risk of gap maloperation. Under two-phase disconnection faults, PV suppressed the overvoltage amplitude. But the voltage dropped from 72.02 kV into the same critical range, reducing the reliability of gap operation and increasing the risk of insulation coordination failure. Under lightning faults, PV integration had little influence on the transient neutral-point overvoltage. Conclusions: The conventional fixed-gap protection scheme is no longer fully suitable for the more complex voltage behavior introduced by PV integration. The proposed controllable gap strategy based on amplitude-time dual criteria can effectively avoid maloperation and failure-to-operate risks in the critical range.
[1] 杨智,詹江杨,徐星,等.变压器中性点过电压分析与绝缘配合[J].电测与仪表,2023,60(10):30-35.YANG Z,ZHAN J Y,XU X,et al.Overvoltage analysis and insulation coordination of transformer neutral point[J].Electrical Measurement & Instrumentation,2023,60(10):30-35.
[2] 孙华东,徐式蕴,贺静波,等.高比例电力电子电力系统过电压(一):定义、分类及相关要求[J].中国电机工程学报,2024,44(1):22-34.SUN H D,XU S Y,HE J B,et al.Overvoltage of the power system integrated with high proportion of power electronics (I):Definition,classification and relevant requirements[J].Proceedings of the CSEE,2024,44(1):22-34.
[3] 周郅皓,刘倩,周杭霞.结合环境变量的分布式光伏电站效率评估方法[J].中国计量大学学报.2021,32(1):101-108.ZHOU Z H,LIU Q,ZHOU H X.Efficiency evaluation method of distributed PV stations considering environmental variables[J].Journal of China University of Metrology,2021,32(1):101-108.
[4] 姜淼,徐光福,李正红,等.含逆变型分布式电源配电网的接地故障中性点电压分析及对策[J].电力建设,2018,39(5):70-76.JIANG M,XU G F,LI Z H,et al.Analysis on neutral point overvoltage during grounded fault in distribution network with inverter-interfaced DGs and countermeasures[J].Electric Power Construction,2018,39(5):70-76.
[5] 杨鑫,戴何笠,石海鹏,等.复合羊角间隙与避雷器并联的变压器中性点保护[J].电网技术,2016,40(2):620-625.YANG X,DAI H L,SHI H P,et al.Transformer neutral protection method of composite horn gap parallel to surge arrester[J].Power System Technology,2016,40(2):620-625.
[6] 严玉婷,鲁海亮,王亚舟,等.用于110 kV变压器中性点的新型棒-板-棒组合保护间隙[J].高电压技术,2015,41(2):699-704.YAN Y T,LU H L,WANG Y Z,et al.A new rod-plate-rod combined protection gap for 110 kV transformer neutral point[J].High Voltage Engineering,2015,41(2):699-704.
[7] 李博江,文习山,严玉婷,等.110 kV变压器中性点水流保护间隙与避雷器并联保护方式[J].高电压技术,2014,40(3):772-779.LI B J,WEN X S,YAN Y T,et al.Protection mode of parallel connection of water flow protection gap and arrester for neutral points of 110 kV power transformers[J].High Voltage Engineering,2014,40(3):772-779.
[8] 许鸣昌.110 kV变压器中性点可控间隙的研究[D].北京:华北电力大学,2016:23-38.XU M C.Sutdy on Controlled Gap of 110 kV Transformer Neutral Point[D].Beijing:North China Electric Power University,2016:23-38.
[9] 戴何笠,刘能,王旭,等.变压器中性点并联保护间隙距离确定方法研究[J].电瓷避雷器,2017(3):147-152.DAI H L,LIU N,WANG X,et al.Research on the method of determining the gap distance of parallel protection for transformer neutral point[J].Insulators and Surge Arresters,2017(3):147-152.
[10] ZHANG M,SUN X F,TENG J X,et al.Standing wave compensation based harmonic propagation mitigation for closed-loop distribution feeder[J].IEEE Transactions on Power Electronics,2024,39(11):14142-14147.
[11] SHI Y D,LIU Z,LIU J J,et al.A decentralized secondary voltage control method with unbalance voltage compensation capability for parallel inverters in islanded microgrids[J].IEEE Transactions on Power Electronics,2025,40(8):11564-11582.
[12] 贾科,汪执雅,戴明,等.分布式光伏接入对110 kV主变中性点电压的影响分析[J].电力自动化设备,2018,38(11):181-186.JIA K,WANG Z Y,DAI M,et al.Influence of distributed PV integration on neutral point voltage of 110 kV main transformer[J].Electric Power Automation Equipment,2018,38(11):181-186.
[13] HU Z,HAN Y,YANG P,et al.Evaluation of lightning overvoltage at neutral point of HVDC converter transformer based on EMTP[J].Energy Reports,2022,8:274-283.
[14] ALIPIO R,DE CONTI A,VASCONCELLOS F,et al.Tower-foot grounding model for EMT programs based on transmission line theory and Marti’s model[J].Electric Power Systems Research,2023,223:109584.
[15] 中华人民共和国住房和城乡建设部,中华人民共和国国家质量监督检验检疫总局.交流电气装置的过电压保护和绝缘配合设计规范:GB/T 50064—2014[S].北京:中国标准出版社,2014.
[16] 李云阁.ATP-EMTP及其在电力系统中的应用[M].北京:中国电力出版社,2016:229-235.
[17] RAJU K,PRASAD V.Modelling and validation of metal oxide surge arrester for very fast transients[J].High Voltage,2018,3(2):147-153.
[18] 梁亮,詹智民,邓小磊,等.基于电导增量法的太阳能光伏阵列MPPT仿真[J].郑州大学学报(工学版),2018,39(6):88-92.LIANG L,ZHAN Z M,DENG X L,et al.PV array MPPT simulation based on the conductance increment method[J].Journal of Zhengzhou University (Engineering Science),2018,39(6):88-92.
[19] 国家市场监督管理总局,国家标准化管理委员会.光伏发电站接入电力系统技术规定:GB/T 19964—2024[S].北京:中国标准出版社,2024.
基本信息:
中图分类号:TM615;TM40
引用信息:
[1]韦沅利,王颖,彭永康,等.分布式光伏接入对变压器中性点过电压特性的影响研究[J].中国计量大学学报,2026,37(01):71-81.
基金信息:
国家自然科学基金项目(No.52377017); 国网浙江省电力有限公司科技项目(No.B311TZ25Z001)